Installation of a power panel (M/C 1HPCS) in Unit 1 Reactor Building Annex (November 1) Power panel (M/C 1HPCS) installation completed on November 1, 2012 (Photo taken on November 5, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
2 |
写真 |
Installation of the control panel (high voltage panel) and the generator of the emergency diesel generator (H system) in Unit 1 Reactor Building Annex (November 9) High voltage panel installation completed on November 9, 2012 (Photo taken on December 4, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
3 |
写真 |
Installation of the control panel (high voltage panel) and the generator of the emergency diesel generator (H system) in Unit 1 Reactor Building Annex (November 9) Generator (rotor) installation (Photo taken on October 23, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
4 |
写真 |
Installation of the control panel (high voltage panel) and the generator of the emergency diesel generator (H system) in Unit 1 Reactor Building Annex (November 9) Generator installation completed on November 1, 2012 (Photo taken on November 27, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
5 |
写真 |
Installation of the power panel (P/C 2C-2) in Unit 2 Seawater Heat Exchanger Building (November 12) Function check completed on November 12, 2012 (Photo taken on November 12, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
6 |
写真 |
Permanent installation of the generators of the residual heat removal system cooling systems (A and C) in Unit 2 Seawater Heat Exchanger Building (November 28) Switching to the permanent cable completed (Photo taken on November 21, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
7 |
写真 |
Permanent installation of the generators of the residual heat removal system cooling systems (A and C) in Unit 2 Seawater Heat Exchanger Building (November 28) Trial operation [Permanent operation completed on November 28, 2012] (Photo taken on November 28, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
8 |
写真 |
Generator of the residual heat removal system cooling system (C) Before switching to the permanent cable (Photo taken on November 20, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
9 |
写真 |
Generator of the residual heat removal system cooling system (C) Permanent cable installation (Photo taken on November 20, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
10 |
写真 |
Generator of the residual heat removal system cooling system (C) Switching to the permanent cable completed (Photo taken on November 21, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
11 |
写真 |
Generator of the residual heat removal system cooling system (C) Trial operation [Permanent operation completed on November 28, 2012] (Photo taken on November 28, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
12 |
写真 |
Permanent installation of the generators of the residual heat removal system cooling seawater systems(A and C) in Unit 2 Seawater Heat Exchanger Building (November 29) Taking cable core out of the permanent cable for the generator of the residual heat removal system cooling seawater system pump c (Photo taken on September 22, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
13 |
写真 |
Permanent installation of the generators of the residual heat removal system cooling seawater systems(A and C) in Unit 2 Seawater Heat Exchanger Building (November 29) Switching to the permanent cable completed for the generator of the residual heat removal system cooling seawater system pump c (Photo taken on November 22, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
14 |
写真 |
Permanent installation of the generators of the residual heat removal system cooling seawater systems(A and C) in Unit 2 Seawater Heat Exchanger Building (November 29) Trial operation of the generator of the residual heat removal system cooling seawater system pump (C) [Permanent installation completed on November 29, 2012] (Photo taken on November 22, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
15 |
写真 |
Permanent installation of the generator of the emergency diesel generator cooling system (A) in Unit 2 Seawater Heat Exchanger Building (November 26) Permanent cable installation (Photo taken on November 21, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
16 |
写真 |
Permanent installation of the generator of the emergency diesel generator cooling system (A) in Unit 2 Seawater Heat Exchanger Building (November 26) Taking cable core out of the permanent cable (Photo taken on November 21, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
17 |
写真 |
Permanent installation of the generator of the emergency diesel generator cooling system (A) in Unit 2 Seawater Heat Exchanger Building (November 26) Permanent cable installation completed (Photo taken on November 21, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
18 |
写真 |
Permanent installation of the generator of the emergency diesel generator cooling system (A) in Unit 2 Seawater Heat Exchanger Building (November 26) Permanent installation completed on November 26, 2012 (Photo taken on November 27, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
19 |
写真 |
Permanent installation of the generator of the component cooling water system (A) in Unit 2 Seawater Heat Exchanger Building (November 29) Before switching to the permanent cables (Photo taken on November 27, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|
20 |
写真 |
Permanent installation of the generator of the component cooling water system (A) in Unit 2 Seawater Heat Exchanger Building (November 29) Permanent cable terminal installation (Photo taken on November 27, 2012)
(上位階層ページタイトル/会議名: Progress Status of Fukushima Dai-ni Nuclear Power Station Restoration Plan (Monthly Report: November 2012))
情報提供機関: 東京電力
掲載日/会議開催日: 2012-12-05
|