No. タイトル 情報提供機関/著者 掲載日/会議開催日
1 Fixed point monitoring status by temporary monitoring post at Fukushima Daiichi Nuclear Power Station monitoring data by a monitoring car at Fukushima Daiichi Nuclear Power Station [Measurement Date; 2014-01-28]保存されたウェブページへ TEPCO 2014-01-28
2 Fixed point monitoring status by temporary monitoring post at Fukushima Daiichi Nuclear Power Station monitoring data by a monitoring car at Fukushima Daiichi Nuclear Power Station [Measurement Date; 2014-01-28]保存されたウェブページへ TEPCO 2014-01-28
3 The parameters related to the plants (Summary Chart) [as of 5; 00 January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
4 The parameters related to the plants (Summary Chart) [as of 11; 00 January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
5 Situation of water level, transfer and treatment of the accumulated water [9; 00 on January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
6 Nuclides analysis result of the radioactive materials in the air at Fukushima Nuclear Power Stations [2014-01-28]保存されたウェブページへ TEPCO 2014-01-28
7 Nuclides analysis result of the radioactive materials in the seawater coast, Fukushima Daiichi Nuclear Power Station [2014-01-28]保存されたウェブページへ TEPCO 2014-01-28
8 Radioactivity density of the seawater in the port of Fukushima Daiichi Nuclear Power Station [January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
9 Nuclides analysis result of the sub-drain of Fukushima Daiichi Nuclear Power Station [January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
10 Nuclides analysis result of the sub-drain water in the surroundings of the Central Radioactive Waste treatment facility [January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
11 Summary of marine soil monitoring result ; Fukushima Daiichi Nuclear Power Station [December 2013]保存されたウェブページへ TEPCO 2014-01-28
12 Nuclides analysis result of the radioactive materials in the seawater offshore of Miyagi Prefecture [January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
13 Results of the radioactive material analysis related to the leaked water from the pipeline connecting from desalination system (Reverse Osmosis Membrane) to concentrated water storage tank in Fukushima Daiichi Nuclear Power Station Unit 1 to 4 side of South Discharge Channel [January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
14 Detailed analysis results in the port of Fukushima Daiichi Nuclear Power Station, around discharge channel and bank protection (Sampling Locations of underground water Obtained at Bank Protection) 2014-01-28保存されたウェブページへ TEPCO 2014-01-28
15 Detailed analysis results in the port of Fukushima Daiichi Nuclear Power Station, around discharge channel and bank protection (2)保存されたウェブページへ TEPCO 2014-01-28
16 Underground reservoir nuclide analysis results (As of January 27, 2014) - underground reservoir observation holes nuclide analysis results (As of January 27, 2014) - nuclide analysis results of the underground bypass (Investigation holes/Pumping Well) and the sea side observation holes (As of January 27, 2013)保存されたウェブページへ TEPCO 2014-01-28
17 Sampling results Regarding the water leak at the Tanks in the H4 area in Fukushima Daiichi Nuclear Power Station (South water outlet, drainage channel) 2014-01-28保存されたウェブページへ TEPCO 2014-01-28
18 Sampling results Regarding the Influence on the water leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Around the H4 Area) [January 28, 2014]保存されたウェブページへ TEPCO 2014-01-28
19 福島第一原子力発電所 地下貯水槽・貯水槽観測孔・地下水バイパス、海側観測孔分析結果 [2014年01月27日; 採取]保存されたウェブページへ 東京電力 2014-01-28
20 東京電力(株)福島第一原子力発電所の20km圏内の空間線量率測定結果 [2014年01月28日~2014年01月30日; 測定]保存されたウェブページへ 原子力規制委員会 2014-01-28