1 Fixed point monitoring status by temporary monitoring post at Fukushima Daiichi Nuclear Power Station monitoring data by a monitoring car at Fukushima Daiichi Nuclear Power Station [Measurement Date; 2014-04-16]保存されたウェブページへ TEPCO 2014-04-16
2 Fixed point monitoring status by temporary monitoring post at Fukushima Daiichi Nuclear Power Station monitoring data by a monitoring car at Fukushima Daiichi Nuclear Power Station [Measurement Date; 2014-04-16]保存されたウェブページへ TEPCO 2014-04-16
3 The parameters related to the plants (Summary Chart) [as of 5; 00 April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
4 The parameters related to the plants (Summary Chart) [as of 11; 00 April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
5 Situation of water level, transfer and treatment of the accumulated water [9; 00 on April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
6 Nuclides analysis result of the radioactive materials in the air at Fukushima Nuclear Power Stations [2014-04-16]保存されたウェブページへ TEPCO 2014-04-16
7 Nuclides analysis result of the radioactive materials in the seawater coast, Fukushima Daiichi Nuclear Power Station [2014-04-16]保存されたウェブページへ TEPCO 2014-04-16
8 Radioactivity density of the seawater in the port of Fukushima Daiichi Nuclear Power Station [April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
9 Nuclides analysis result of the sub-drain water in the surroundings of the Central Radioactive Waste treatment facility [April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
10 Nuclides analysis result of the radioactive materials in the seawater offshore of Miyagi Prefecture [April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
11 Results of the radioactive material analysis related to the leaked water from the pipeline connecting from desalination system (Reverse Osmosis Membrane) to concentrated water storage tank in Fukushima Daiichi Nuclear Power Station Unit 1 to 4 side of South Discharge Channel [April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
12 Detailed analysis results in the port of Fukushima Daiichi Nuclear Power Station, around discharge channel and bank protection (Sampling Locations of underground water Obtained at Bank Protection) 2014-04-16保存されたウェブページへ TEPCO 2014-04-16
13 Underground reservoir nuclide analysis results (As of April 15, 2014) - nuclide analysis results of the underground bypass (Investigation holes/Pumping Well) and the sea side observation holes (As of April 15, 2014)保存されたウェブページへ TEPCO 2014-04-16
14 Tritium analysis results of the underground bypass (Investigation holes/pumping well) and the sea side observation holes (As of April 7 and 8, 2014)保存されたウェブページへ TEPCO 2014-04-16
15 Sampling results Regarding the water leak at the Tanks in the H4 area in Fukushima Daiichi Nuclear Power Station (South water outlet, drainage channel) 2014-04-16保存されたウェブページへ TEPCO 2014-04-16
16 Sampling results Regarding the Influence on the water leak at a Tank in the H4 area in Fukushima Daiichi Nuclear Power Station (Around the H4 Area) [April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
17 Additional sampling results of sub-drain water on west side of Incineration Workshop Building [April 16, 2014] (1)保存されたウェブページへ TEPCO 2014-04-16
18 Additional sampling results of sub-drain water on west side of Incineration Workshop Building [April 16, 2014] (2)保存されたウェブページへ TEPCO 2014-04-16
19 Sampling results Regarding the Influence on the water leak at a Tank in the H6 area in Fukushima Daiichi Nuclear Power Station (Around the H6 Area) [April 16, 2014]保存されたウェブページへ TEPCO 2014-04-16
20 福島第一原子力発電所 地下貯水槽 分析結果 [2014年04月15日; 採取]保存されたウェブページへ 東京電力 2014-04-16